On November 24, PPM Express added two task types in version 28.16: Fixed Duration and Fixed Effort. They are available alongside the existing Fixed Units type. For a small project team, one important difference appears when a task loses its last assignee.
One change, two results
According to PPM Express’s extended release notes, removing the last assignee from a Fixed Duration task keeps duration unchanged and resets effort to zero. Doing the same to a Fixed Effort task keeps both effort and duration. In the first case, zero hours can be the result of recalculation, not the absence of work. In the second, the retained hours do not mean someone is assigned.
What to check before changing a live plan
The scheduling guide says the project must use Calculate Progress by = Effort for these types. Use native PPM Express tasks in Auto mode for this check. In a test project, use Set Task Type to configure one task of each new type, give both nonzero effort, assign one test assignee to each and record the starting values. Remove both assignments and check three fields on each task: effort, duration and the assignee list. If the team carries those figures into reports for a manager, check separately how it flags tasks with no assignee. Do not use zero hours or a retained estimate as a substitute for that flag.
The guide clarifies that changing the project’s default task type does not recalculate existing tasks. The release notes do not specify availability by plan. Nadali did not change settings in a work account.
Takeaway: when handing off a task, check not just the hours but whether a new owner is assigned.