Tools2 min read

Aconex adds separate deadlines for parallel document reviews

Document Processes adds separate deadlines and outcome options for parallel review steps. Here is how a small project team can check the rollout.

Prepared by the NADALI editorial team using AI

Hands above architectural drawings on a worktable.
Tima Miroshnichenko / Pexels (stock illustration) · Pexels License — https://www.pexels.com/license/ · 1440 × 960

Oracle Aconex’s November update adds separate deadlines and outcome options for parallel document review steps in Document Processes. For a small contractor or design practice, it is a chance to check whether two teams can follow different deadlines in one review route without separate email reminders.

Who gets it, and when

Oracle’s schedule lists November 21, 2026 as the EU1 rollout start and November 22 as the CA1 start. These are start dates, not guarantees that the feature is already visible in your project: Oracle rolls out updates to each instance gradually over a 30-day period. The change is for Document Processes, not the separate Workflows module.

What to check before changing a rule

  1. Open Document Processes → Review Matrix with your project administrator and check that parallel steps have their own settings. Editing a rule does not update reviews already started from that rule.
  2. In an authorized test project, use one test document and assign a Lead Reviewer to each of two parallel steps. For example, allow an engineer two days to check completeness and an estimator four days to verify quantities. Check which deadline and outcome options each Lead Reviewer sees. Two and four days are illustrative, not Oracle’s recommendations or Nadali test results.
  3. Separate the final decision from completion of the parallel steps. According to Oracle’s documentation, if the last stage has parallel steps, the last step to finish determines the final review outcome. If a designated role needs to make the final decision, Oracle recommends using one step in the final stage.

Start with one new review route rather than changing every active project. For a broader look at delays, see how to use an event log to distinguish work from waiting. 

Sources and verification

  1. Oracle Aconex — November 2026 release notes ↗
    Source checked: 2026-11-23
  2. Oracle Aconex — Create and manage review rules for Document Processes ↗
    Source checked: 2026-11-23